PT Perusahaan Listrik Negara (PLN) claimed, Mitsubishi became one of the
partners enter the selection to accompany PT Indonesia Power to build Java 5
steam power plant with a capacity of 2,000 megawatts in Banten. However, the
beauty contest is still ongoing.
PLN Procurement Director, Iwan Supangkat stated, PLN pointing Indonesia
Power for work on Java 5 steam power plant, because the company already has
several facilities of Suralaya 1 steam power plant to Suralaya 7 steam power
plant. The PLN's subsidiary has also done a feasibility study and the center
has land for development projects the.
As for who will act as a partner of Indonesia Power is so far still in
the selection and Mitsubishi entered in the selection. "Partners will be
selected, the machine tendered. So, not necessarily Mitsubishi wins. Whoever
the best chance to win," he said.
Iwan ensure, if nothing goes wrong, the construction of the steam power plant will begin in January 2017.
He also stated that the project is completed within three years. "The
target for completion in late 2019," said Iwan.
All complete data can be seen at www.tender-indonesia.com
(The source of the Indonesia Oil and Gas,
Mining, Electricity, Infrastrcuture, Telecommunication tender project and
tender award)
semoga dengan adanya MITSUBSHI, CANDIDATES PARTNERS OF INDONESIA POWER IN JAVA 5 STEAM POWER PLANT PROJECT
BalasHapusakan bisa membuka lapangan pekerjaan yang banyak ka ini aku mau reccomend tentang HOSTEL MURAH DI BANDUNG COCOK UNTUK BACKPACKER aku reccomed banget nih buat yang bingung cari penginapan di daerah bandung