[CATEGORY: MINING]
PT Agincourt Resources, the owner and operator of the Martabe gold mine
in South Tapanuli Regency, North Sumatra Province, stated that the mine
delivered a strong production performance in the first quarter of 2016.
Tim Duffy, President Director and Managing Director of Agincourt said in
a press statement that the company's processing plant milled as much as 1.215
million tons of ore that produced 78,171 ounces of gold and 573,892 ounces of
silver during the quarter.
Duffy explained that the capital spent through the first quarter was US$
8.2 million, whilst the exploration expenditures are expected to be
approximately $ 2.19 million. "Our annual capital expenditures are
expected to be approximately $ 67 million while exploration expenditures are
expected to be approximately $ 12 million," he said.
According to Duffy the firm is currently in preparation to install a
secondary crusher, planned to take place next year, and to be commissioned in
2017, which will enable Martabe to increase process plant throughput to 5
million tons per annum.
Another important progress of Martabe, Duffy added, is application to
the government to develop and operate the Barani and Ramba Joring Pits.
"These are much smaller than the existing Purnama pit and together will
extend the life of mine at Martabe by 2 years from 10 years we initially have
with only Purnama Pit."
All complete data can be seen at www.tender-indonesia.com
(The source of the Indonesia Oil and Gas,
Mining, Electricity, Infrastrcuture, Telecommunication tender project and
tender award)
MARTABE GOLD MINE DELIVERS STRONG PERFORMANCE semoga hasilnya melimpah ya ka ka ini aku mau reccomend tentang HOSTEL MURAH DI BANDUNG COCOK UNTUK BACKPACKER aku reccomed banget nih buat yang bingung cari penginapan di daerah bandung
BalasHapus