Senin, 26 September 2016

2019, CONSTRUCTION OF 29 NEW DAM COMPLETION






[CATEGORY: INFRASTRUCTURE]
  
The Ministry of Public Works and Public Housing target as many as 29 new dam construction could be completed by 2019.

As many as 65 dams until 2022 that the government planned to be built will be completed.

"Target the dam was completed a total of 29 new dams by 2019 which will increase water storage be 14.42 billion cubic meters (m3)," said Head of Dams Directorate General of Water Resources, the Ministry of Public Works and Public Housing, Imam Santoso.

Based on data from the Directorate General of Water Resources, in 2015 has finished five dams. Five dams which have been completed in 2015, among others Rajui Dam (Aceh), Jatigede Dam (West Java), Bajulmati Dam (East Java), Nipah Dam (East Java), and Titab Dam (Bali).

Then, he continued, the dam will be completed in 2016, the Paya Seunara Dam (Aceh) dan Teritip Dam (East Kalimantan). In 2017, Raknamo and Mila Dam (NTT), Tanju Dam (NTB), and Marangkayu Dam (East Kalimantan) is targeted for completion. Then in 2018 the seven dam will be completed, namely Gondang  Dam (Central Java), Tugu Dam (East Java), Logung Dam (Central Java), Rotiklod Dam (NTT), Sei Gong Dam (Riau), Bintang Bano Dam (NTB), as well as Kuningan Dam (West Java).

In 2019, there were 11 dams are targeted to be completed in between that Passeloreng Dam (South Sulawesi), Tapin Dam (South Kalimantan), Ciawi Dam (West Java), Sukamahi Dam (West Java), Karalloe Dam (South Sulawesi), Sindang Heula Dam (Banten), Keureuto Dam (Aceh), Bendo Dam (East Java), Gongseng Dam (East Java), and Pidekso Dam (Central Java).

Imam continued, Ministry of Public Work and Public Housing currently building 24 dams that consists of 11 dam advanced unfinished was built in 2014 and 13 new dam was built since 2015. As for this year will be built eight new dams.

Furthermore, in 2017 there will be an additional nine dams, and in 2018 there were 11 dams and in 2019 there were eight dams will be constructed so that a total of 65 dams. As for the overall construction of 65 dams to be completed in 2022.

Imam added that the financing needs to build 65 dams is estimated at Rp 70,1 trillion sourced from the state budget Rp 64.04 trillion and Chinese loan Rp 4.82 trillion for Jatigede dam and loans from South Korea Rp 1.26 trillion to build Karian Dam.


Reference :
1.     Head of Dams Directorate General of Water Resources, the Ministry of Public Works and Public Housing, Imam Santoso.


All complete data can be seen at www.tender-indonesia.com
(The source of the Indonesia Oil and Gas, Mining, Electricity, Infrastrcuture, Telecommunication tender project and tender award)
 

1 komentar:

  1. 2019, CONSTRUCTION OF 29 NEW DAM COMPLETION??wow o iy ka "Zapplerepair pengerjaan di tempat. Zapplerepair memberikan jasa service onsite home servis pengerjaan di tempat khusus untuk kota Jakarta, Bandung dan Surabaya dengan menaikan level servis ditambah free konsultasi untuk solusi di bidang data security, Networking dan performa yang cocok untuk kebutuhan anda dan sengat terjangkau di kantong" anda (http://onsite.znotebookrepair.com)