[CATEGORY : ELECTRICITY]
Cilacap Steam Power Plant Expansion Phase
II to be operational in mid 2019. The power plant was built by PT Sumber Segara
Primadaya (SSP) which is owned by PT Sumberenergi Sakti Prima (SSP) by 51% and
PT Pembangkit Jawa Bali (PJB) 49%. Completion of these projects carried out
three months ahead of target. At first the project is scheduled to take 39
months from September 2016 and be operational by the end of 2019, but
accelerated to mid 2019. Cilacap Power Plant Expansion Project value is US$ 1.4
billion.