CILACAP STEAM POWER PLANT PROJECT PHASE II ACCELERATED






[CATEGORY : ELECTRICITY]
 
Cilacap Steam Power Plant Expansion Phase II to be operational in mid 2019. The power plant was built by PT Sumber Segara Primadaya (SSP) which is owned by PT Sumberenergi Sakti Prima (SSP) by 51% and PT Pembangkit Jawa Bali (PJB) 49%. Completion of these projects carried out three months ahead of target. At first the project is scheduled to take 39 months from September 2016 and be operational by the end of 2019, but accelerated to mid 2019. Cilacap Power Plant Expansion Project value is US$ 1.4 billion.