Progress girder
installation in zone 5 light rail transit (LRT) of Jakabaring continues to
speed up the contracting parties. Even after the review by the Governor of
South Sumatra, Alex Noerdin some time ago, in the zone now installs faster
construction.
Installation girder by
workers on 24 hours so that the target can be completed by the end of 2017.
Installation of girder cranes lifted the steel cords on both sides and then
pulled up.
The fixtures were used on
erection girders consist of a one unit crawler crane capacity of 150 ton,
launching gantry capacity 70 ton, gantry, one unit mobile crane capacity of 50
ton (crane service), boogie and trailer.
LRT project manager Zona
5, Erwin Martoras explained, the phase is being done in the working area zone
already entered the phase of girder. While some areas towards the depot is
still under construction of pier head and drill pile.
"No problems at this
time, the progress of ongoing and targeted all phase according to plan until
completed installation trajectory," said Erwin.
He added, 600 beam girder
which was originally installed is now only a quarter of the amount already set
up, after the installation will be performed casting steel plate as a train
track. Recognized girder installation continues gradually to zone 5 to connect
to the other zones.