Selasa, 30 Agustus 2016

18 GIRDER INSTALLED, CONSTRUCTION LRT






[CATEGORY: INFRASTRUCTURE]
 
Progress girder installation in zone 5 light rail transit (LRT) of Jakabaring continues to speed up the contracting parties. Even after the review by the Governor of South Sumatra, Alex Noerdin some time ago, in the zone now installs faster construction. 

Installation girder by workers on 24 hours so that the target can be completed by the end of 2017. Installation of girder cranes lifted the steel cords on both sides and then pulled up.

The fixtures were used on erection girders consist of a one unit crawler crane capacity of 150 ton, launching gantry capacity 70 ton, gantry, one unit mobile crane capacity of 50 ton (crane service), boogie and trailer.

LRT project manager Zona 5, Erwin Martoras explained, the phase is being done in the working area zone already entered the phase of girder. While some areas towards the depot is still under construction of pier head and drill pile.

"No problems at this time, the progress of ongoing and targeted all phase according to plan until completed installation trajectory," said Erwin.

He added, 600 beam girder which was originally installed is now only a quarter of the amount already set up, after the installation will be performed casting steel plate as a train track. Recognized girder installation continues gradually to zone 5 to connect to the other zones.


All complete data can be seen at www.tender-indonesia.com
(The source of the Indonesia Oil and Gas, Mining, Electricity, Infrastrcuture, Telecommunication)