Construction of Trans-Java toll road Batang-Semarang
segments, Central Java, accelerated to be crossed by travelers on Lebaran next
year although the land acquisition not yet complete. Targeted Batang-Semarang
can already be crossed when the current ongoing Lebaran 2017. Construction
section 1 and II Batang-Tulis-Weleri stated already exceeded the target, on the
plan 2.39% has been realized 3.32%. As for the land toll road section III along
the 12.15 km, is still in the process of land acquisition.