PT Citra Waspphutowa targeting construction of
Depok-Antasari toll road project or Desari
section I Antasari-Andara along 3.61 kilometers can be completed in May
next year and operate three months. Currently the construction progress to
sections 1 to 49%. So far the company has spent around Rp 400 billion bailout
and will grow to chase the target of 100% land acquisition for the section I.
As for construction, the company claimed to have met the needs total investment
of Rp 3 trillion. Desari toll road construction itself consists of five
sections managed by PT Citra Waspphutowa, a joint venture company PT Citra
Marga Nusaphala Persada Tbk. (62.50)% with Waskita PT Karya Tbk. (12.50%), PT
Waskita Toll Road 12:50%, and PT Pembangunan Perumahan (12.50%).
All complete data can be seen at www.tender-indonesia.com
(The source of the Indonesia Oil and Gas,
Mining, Electricity, Infrastrcuture, Telecommunication tender project and
tender award)